1 - rigid floor with a thickness of min. 150 mm
2 - plastic or metal pipe, diameter "D" i wall thickness "t"
3 - continuous insulation made of flexible elastomeric foam (FEF), thickness "g",
density nominal 45 ÷ 70 kg / m3 and reaction to fire class BL-s2, d0 according to
EN 13501-1
4 - CarboCollar CC fireproof collar, mounted at the bottom of the floor
5 - fireproof collar fastening - expansion anchor bolts M6x60 or M8x80
6 - the space between the pipe and the wall structure, filled with mortar cement, with
thickness u = max. 10 mm
* Detailed information can be found at ETA
Fill the space between the pipe insulation and the aperture tightly. Use cement mortar
Place fireproof collar on the pipe insulation. In case of fireproof collars with a diameter of CC-125 and larger with a segmented cover S, first wrap the pipe four times with an intumescent insert and then put the steel cover it
Pull the locking pin of the clamping buckle through the fixing slot on the other end of the fireproof collar and fold it 180 ° backwards so that the collar is firmly closed on the pipe insulation
Attach the fireproof collar to the floor using expansion anchor bolts
Mark the completed penetration seal with the label attached to the set. Mark CarboCollar fireproof collar on the label, enter the date and the name
METHOD OF SEALING METAL AND PLASTIC PIPE IN FEF INSULATION PENETRATING RIGID FLOOR ACCORDING TO ETA-16/0189*
INSTALLATION OF CARBOCOLLAR CC FIREPROOF COLLAR ON A METAL AND PLASTIC PIPE IN INSULATION WITH ELASTOMERIC FEF (RUBBER) FOAM PENETRATING THE FLOOR